HULK was prequalified in late 2025 as a demolition and site work subcontractor on the Tacoma Housing Authority's Salishan-Hillside redevelopment in East Tacoma. Our crews handle the work area by area as each building location opens up.
- Dec 2025Staging area rock, filter fabric and wattle install
- Feb 2026Mobilized for demolition at locations 2.1 & 2.4
- Mar 2026Extra concrete and asphalt removal, rock import and grading at 2.1
- Jun – Jul 2026Building 2.29 grading, ADA concrete at 2.01 & 2.04, 2.4 demo, sidewalk and asphalt
- Aug – Sep 2026Utility potholing and mailbox base excavation